ROAD CONSTRUCTION UPDATE FOR THE WEEK OF January 29 THROUGH February 4, 2018
top of page
  • avdailynews.com

ROAD CONSTRUCTION UPDATE FOR THE WEEK OF January 29 THROUGH February 4, 2018


East side of Division Street from 100’ south of Gaitano Drive to northeast corner of Bolero Drive

Intermittent lane and shoulder closures for landscape assessment district renovation.

Avenue S will be closed east bound on the east side of 47th East with a detour to R-8 at from 9 pm to 5 am Monday through Friday

Street closure with detour in place for Southern California Gas Company to work on gas main. Work began December 4 and is expected to last four to six weeks.

Avenue S at Parkwood Drive and at The Groves

Intermittent lane closures for Traffic signal conduit installation.

22nd Street East between Avenue Q-6 to Palmdale Blvd.

Intermittent lane and shoulder closures for street improvements.

Avenue R and 40th Street East

Intermittent lane and shoulder closures for the Guidance Charter School utility installation and street improvements. Expect delays.

STREET CLOSURE WITH DETOUR

35th East will be closed to through traffic between Avenue Q-10 and Palmdale Blvd.

This will be a street closure with a detour in place. Work is being done for the installation of water, storm drain and street improvements for the new Palmdale Aerospace Academy.

For more information, call the public works department at 661/267-5300